Home
Our Projects
Previous Projects
Pirates of the Caribbean II & III

Pirates of the Caribbean II & III

Client Name and Address
Second Mate Production, Inc.
U.S.A.

Date of Service
December 2004 to November, 2005

Level of Involvement
Generally involved in engineering design and build services, involving various access roads and site improvements to filming locations.

Works Included

  1. Difficult access road to Cannibal Village at High Meadow on road to Soufriere.
  2. Access and civil works for two suspension bridges at Twin Peaks and High Meadow.
  3. Hampstead works including:
    • Temporary by-pass bridge for main highway traffic in order to allow existing bridge to be used in film production.
    • Three (3) additional access roads and shooting sites.
    • Dredging works on Londonderry River.
  4. Various car parks and other miscellaneous works (Laudat, Soufriere, Anse Soldat).
  5. Design and installation of safety cables for stunts at Vieille Case Church.